Construction Site Log – Union Oțel Făgăraș

Employees Service Building P+2, vertical extension of Office Building C4 to P+2, extension of Hall C3, metal canopy, technological annexes, platform development

Details

Location:
Str. Negoiu nr. 136,
Municipiul Făgăraș, jud. Brașov

Total built area:
over 8,400 sqm (after project completion)

Start of works:
August 2025

Video recording date:
September 2025

Estimated completion date:
May 2026

Client:
Union Oțel

Project Manager:
Greavu Natalia

Site Manager:
Rotaru Liviu

Companies involved:
RAP Development – General Contractor
RAP Instal

About

Project status

Work on the Union Oțel – Făgăraș project began in August 2025, and the video footage shot in September 2025 captures the initial stages of site organization and land preparation. Completion of the work is estimated for May 2026.

Works carried out in the current stage (summary)

  • Site organization and installation
  • Site preparation: removal of the existing platform, excavation works and dismantling of the existing asphalt pavement
  • Foundation works: general and local excavations, soil removal, excavation works for consolidation of existing foundations
  • Dismantling and relocation of the existing façade (sandwich panels, steel structure and gates) in order to allow the extension of the production hall

 

The project is part of the RAP Development portfolio.
See other projects carried out by RAP Development in the Projects section.

How can we help?

Use our industrial building configurator if you don’t yet have a clear concept of your project. We’ll get back to you as quickly as we can with an offer.

I would like to receive a tender, but I do not have the project.  

I would like to receive a tender and I do have the project.

I would like to receive a tender and I do have the project.

Please complete the following form by clicking below and we will send you a tender as soon as possible.

astet single