RAP Development successfully implemented a large project for our partner, ERTEX INTERNATIONAL. A greenfield investment with a production hall, storage room, and office space totaling more than 8,000 square meters. The project began on an empty plot of land with no infrastructure, and the finished product was an industrial unit that was completely operational.
#logisticspace #factory #office #textile

Details

Beneficiary
Ertex International

Industry
Textile

Construction type
Factory, Warehouse, Offices

City
Brașov

Built surface
8.000mp

About

Exterior works:

  • Two fire water reserves of fire water for hydrants and sprinklers
  • Pump station building
  • Gatehouse
  • Rain water retention basin
  • Perimeter fencing (galvanized edged mesh panels with reinforced concrete base)
  • Access gates: pedestrian + car access
  • Other exterior works: for approx. 3,500 sqm of roads, platforms, sidewalks (asphalt, concrete, paved or macadam) and landscaping

Main building- resistance works:

  • Infrastructure: includes isolated foundations made of monolithic foundation blocks, and monolithic reinforced concrete technological channels beneath the entire production space;
  • The floor elevation of ±0.00, made of reinforced concrete with welded mesh
  • For the Superstructure part:
    Building – Production and storage hall: precast reinforced concrete pillars; main transverse metal beams made of welded plates with variable section;  and beams with longitudinal metallic secondary lattices
  • Technological and administrative buildings: the main and secondary metal structure made with monolithic reinforced concrete slab in a collaborative system.

Main building- architectural works:

  • For the external walls we installed a system consisting of structural boxes + mineral wool + sinus facade board;
  • The roofing works include a system consisting of self-supported corrugated iron, mineral wool and PVC membrane with perimeter attic;
  • The interior compartments are made either with fire-resistant sandwich panels with mineral wool or with masonry walls for the technical spaces. Also in the administrative space we have internal partitions made with wall systems made of double-clad plasterboard;
  • Fully equipped sectional doors with hydraulic leveling ramps;
  • The exterior cladding is made of aluminum. For the interior carpentry we used simple metal or RF pedestrian doors, interior doors systems made in fire-resistant walls consisting of quick PVC doors doubled by fire-resistant sliding doors;
  • In the administrative building, the interior carpentry includes a fire-resistant glass wall for the meeting room, interior glass/mdf doors, etc.
  • Other interior finishes in the administrative building: tiled floors, PVC carpet or carpet depending on the destination of the space, coffered ceilings or plasterboard ceilings, HPL compartments for sanitary groups, etc.

Installations:

  • Plumbing
  • Heating installations
  • Hydrants
  • Sprinklers
  • Ventilation and climate
  • Smoke exhaust system
  • Rainwater installations
  • Electrical installations (strong currents and weak currents)

 +40 725 355 653
development.office@rap-group.ro

How can we help?

Use our industrial building configurator if you don’t yet have a clear concept of your project. We’ll get back to you as quickly as we can with an offer.

I would like to receive a tender, but I do not have the project.  

I would like to receive a tender and I do have the project.

I would like to receive a tender and I do have the project.

Please complete the following form by clicking below and we will send you a tender as soon as possible.

astet single