Construction Journal July–August 2025 Puratos – Tunari, Ilfov

Expansion of production and storage capacity through the turnkey design and execution of a new production facility and a closed connecting tunnel to the existing factory.
#PuratosRomaniaProject #FoodIndustryConstruction #FactoryExpansion #TurnkeyConstruction #TeamRAPinAction #EngineeringExcellence #SustainableFoodIndustry

Details

Client:
BEMCHIMMO ROMANIA SRL

Industry:
Food

Project Surface Area:
4,500 sqm – Main Production Hall + Auxiliary Spaces + Internal Roads and Perimeter Fencing

Category:
C – Industrial Class

Location:
Tunari, Ilfov

Project Manager: Mihai Repanovici
Site Manager: Gabriel Pipos

About

Start date:
March 2025

Photo date:
July – August 2025

Completion Date:
December 2025 – New Plant,
June 2026 – Refurbishment of Existing Plant

Section of executed works

  • Warehouse foundation infrastructure
  • Prefabricated concrete structure
  • Prefabricated concrete base panels
  • Steel structure for office area
  • Retaining walls
  • Facade sandwich panel installation (approximately 50%)

 

How can we help?

Use our industrial building configurator if you don’t yet have a clear concept of your project. We’ll get back to you as quickly as we can with an offer.

I would like to receive a tender, but I do not have the project.  

I would like to receive a tender and I do have the project.

I would like to receive a tender and I do have the project.

Please complete the following form by clicking below and we will send you a tender as soon as possible.

astet single